Brief Description | Install new concrete sidewalks, curbs & gutters and bus parking lot. |
Location | Greensboro, NC. |
Project Delivery | CM at Risk |
Size | 50,000 SF and 1,000 LF Curb & Gutter |
Project Schedule | 6 Months |
Architect | Triad Design Group |
Brief Description | Install sidewalks and site furnishing to new activity center. This project has been awarded LEED Gold Status. |
Location | Winston-Salem, NC. |
Project Delivery | CM at Risk |
Size | 15,000 SF |
Project Schedule | 4 Months |
Architect | Woolpert Design Group |
Description | |
Location | Greensboro, NC. |
Project Delivery | CM at Risk |
Size | 30,000 SF |
Project Schedule | 4 Months |
Architect | Perkins Eastman |
Brief Description | Install new concrete sidewalks, curbs & gutters and bus parking lot. |
Location | |
Project Delivery | CM at Risk |
Size | 40,000 SF; 10,000 LF Curb & Gutter |
Project Schedule | 4 Months |
Architect | Pinnacle Architects |